Inside SunZia, the Largest Clean Energy Megaproject in United States History

When the sun sets over central New Mexico, strong gusts sweep through arid canyons, creating a natural phenomenon that locals have compared for centuries to the wails of the folkloric ghost La Llorona. This June, those desert winds began driving more than 900 colossal steel turbines, establishing the largest wind farm on the continent. Spread across a patch of desert roughly the size of Chicago, each turbine stands as tall as the Statue of Liberty. The facility connects to a 550-mile high-voltage transmission line that stretches across the Southwest, ultimately delivering electricity to more than one million homes as far away as California.
Generated electricity from the SunZia project surpasses the output of the Hoover Dam. When the turbines came online this spring, they immediately set records for wind-generated power within California’s grid, complementing daytime solar generation by supplying energy through the night. Developers estimate that by next summer, the project will prevent approximately 9 million metric tons of carbon dioxide from entering the atmosphere.
Yet the journey to completion spanned nearly two decades, encountering a morass of federal and state permitting hurdles, ownership changes, route modifications, and opposition from military installations, tribal communities, and environmental advocates. Proposed initially in 2006 when coal remained the dominant US electricity source and national power demand was largely flat, the project languished for years. Financing proved as significant a barrier as regulatory delay. Even after securing federal approval and a fast-track designation from the Obama administration in 2015, the project stalled due to high costs, state-level resistance, and an energy market that lacked sufficient demand for large-scale renewable power.
By 2022, Pattern Energy assumed full control of the transmission line project alongside its wind development role. The enterprise applied for a revised federal permit to bypass the White Sands Missile Range, securing new approval in under two years. Backed by $11 billion in financing from global financial institutions, pension funds, and clean energy investors, construction moved forward rapidly.

As national electricity demand surges—projected to rise 25 percent by the end of the decade and up to 78 percent by 2050—industry leaders note that market conditions have entirely transformed. However, the project’s survival also depended on evolving relationships with early critics. In New Mexico, Pattern Energy engaged with organizations such as the National Audubon Society to address concerns regarding migratory birds, including the crimson-capped sandhill crane. Developers rerouted lines north, placed them alongside existing infrastructure, and installed bird diverters. These adjustments helped secure a unanimous approval from the New Mexico Public Regulation Commission in 2022 after an earlier version of the route had been rejected in 2018.
Not all concerns were resolved, particularly along the Arizona portion of the route. Environmentalists and Indigenous communities, including the Tohono O’odham Nation and the San Carlos Apache Tribe, have raised sharp objections over transmission lines running through the scenic and culturally sensitive San Pedro Valley. A lawsuit filed by tribal nations and advocates, alleging that developers and the Department of the Interior failed to adequately protect the valley, remains pending in federal court.

Despite ongoing legal disputes, policymakers point to SunZia as a catalyst for broader permitting reform, including Senate proposals designed to streamline federal coordination for interstate transmission lines. Proponents argue that similar large-scale projects will be essential to meet future energy demands and combat extreme weather driven by climate change, provided developers engage early with local and ecological concerns.